Reconnaissance (1:20,000) Fish and Fish Habitat Inventory Pierre and Twain...
The objective of this project was to conduct a Reconnaissance (1:20,000) Fish and Fish Habitat Inventory in several drainages within the Babine Lake watershed group. This is a... -
Exchamsiks Fish Ladder Replacement
The construction of Highway 16 and the Canadian National Railway (CN Rail) cut off two relatively large channels (known as the Exchamsiks Backchannel area) from the Skeena River... -
Enhancing Environmental Values Program
This datasets contains reports for the Enhancing Environmental Values Program, funded as part of Forest Renewal BC. -
Stream Crossing Replacements in the Babine Lake Watershed of the Sutherland...
This datasets contains information about the Stream Crossing Replacements in the Babine Lake Watershed of the Sutherland Operating Area, Vanderhoof Forest District, Northern... -
Kispiox and Cranberry TSA's WRP Document Review
This dataset is a compendium of all outstanding Watershed Restoration Plan (WRP) prescriptions and works in the Kispiox and Cranberry Timber Supply Areas (TSAs). -
Fish Passage Restoration Projects - Telkwa River Watershed
The objective of this project was to assess fish passage at selected culvert bearing road crossings within the Telkwa River watershed. The assessments were carried out at... -
Suskwa Watershed Restoration Program
A list of priorities for restoration sites in the Suskwa Watershed was developed from the Suskwa 1996/97 Fiscal Report. These priorities, prescriptions, and works are... -
West Babine Fish Passage Restoration Project
The project was conducted to improve fish passage at multiple sites in the West Babine watershed. Fish passage was interrupted due to unpassable culverts. The Torkelson... -
Torkelson Watershed Restoration Plan 2001-2005
The purpose of this restoration plan is to outline the Enhancing Environmental Values issues and priorities within the Priority Key Targeted watershed and provide a budget and... -
Lakelse Lake Management Plan
The overall mission of this lake management planning process is to devise methods “to preserve and protect the quality and health of the Lakelse watershed”. This management plan... -
Interim Restoration Plans for the Nine Watersheds in the Central Kalum...
These plans were established as part of Forest Renewal BC requirements to focus restoration efforts on a smaller selection of targeted watershed units. The complete Interim... -
2015 Inventory of High Priority Culverted Fish Passage Barriers
There is no description for this dataset
-
Bulkley River Watershed Connectivity Remediation Plan: 2021-2031
This plan represents the culmination of a collaborative planning process undertaken in the Bulkley River watershed over many months of work with a multi-partner planning team of... -
Effects of rail infrastructure on Pacific salmon and steelhead habitat...
The effects of rail infrastructure on the connectivity of habitat for Chinook (Oncorhynchus tshawytscha), Coho (O. kisutch), Sockeye (O. nerka), Chum (O. keta), and Pink salmon... -
Waterfall Creek Restoration Project 2001
The restoration/rehabilitation works funded through Forest Renewal BC were carried out on Waterfall Creek in late fall of 2001 and consisted of the removal and replacement of... -
Kitwanga Sockeye Salmon Spawning Habitat Improvement Initiative
Since 1999, the Gitanyow Fisheries Authority has been intensively studying the Kitwanga Watershed in an effort to understand the decline of the Kitwanga sockeye stock.... -
Kispiox Watershed Restoration Project
This dataset contains information regarding the Kispiox Watershed Restoration Project, funded through Forest Renewal BC (FRBC). -
Kitwanga River Coho Habitat Enhancement 2005
The Kitwanga River drainage is a tributary of the Skeena River and is located approximately 90 kilometres northwest of Terrace, B.C. The Upper Kitwanga River has excellent... -
Kitseguecla River South Sub-Basin - Monitoring, Assessment, Restoration, Evaluation
This dataset focuses on stream restoration efforts and related activities conducted in the area of the Kitseguekla/Kitseguecla River South Sub-Basin. -
Fish Passage Planning: Falls River Watershed
The Falls River watershed was chosen for assessment planning due to a synergy between the objectives of the British Columbia Ministry of Environment and Climate Change Strategy... -
Kitwanga River South Sub-Basin - Monitoring, Assessment, Restoration
This dataset focuses on stream restoration efforts and related activities conducted in the area of the Kitwanga River South Sub-Basin. -
2000-2001 Interim Watershed Restoration Plan - Lake District
There is no description for this dataset
-
Integrated Watershed Restoration Plan West Babine Watershed
There is no description for this dataset
-
Morice Watershed Restoration Project
This datasets contains information and reports connected to the Morice Watershed restoration project, funded through Forest Renewal BC (FRBC). -
Watershed Restoration Project (WRP) Completion Reports - Forest Renewal BC (FRBC)
These reports summarizes the projects carried out as part of the FRBC funded Watershed Restoration Program/Project (WRP) -
Interim Interior Watershed Restoration Plans
The following document is a compendium of the five Interim Interior Watershed Restoration Plans completed to date. -
Bulkley River Pipeline Crossing - Fish Habitat Assessment
This report informs about the assessment of the aquatic habitat in the area of the proposed pipeline crossing, conducted in 1997. -
Babine Wild Sockeye Habitat Rehabilitation 2016
The primary purpose of the 2016 Babine wild sockeye habitat rehabilitation project was to identify habitat projects that could stop and/or reverse the declines in wild Babine... -
Bushman Creek In-stream Maintenance Works
This document provides insight on the Bushman Creek In-Stream Maintenance Works, targeting the maintenance and repair of approximately 350m of channel extending upstream from... -
Zymoetz (Copper) River Watershed Restoration Program: 16-Km Side Channel (Site 54B)
This dataset focuses on the restoration works conducted at Site 54B, one of the many restoration works conducted along the the Zymoetz (Copper) Rivers in the late 1990s/early... -
Beaver Dam Mitigation and Nuisance Beaver Control
In 2023, the Gitanyow Fisheries Authority (GFA) was contracted by the BC Ministry of Forests to manage beaver dam mitigation and control in the Kitwanga and Nass watersheds. The... -
1st Avenue Culvert Replacements Lakelse Lake
The project focused on the replacement of eleven culverts along 1st Avenue at Lakelse Lake to improve fish passage. -
Bulkley River Bank Stabilization and Riparian Rehabilitation - Telkwa
The project was conducted on a privately owned site (Wittwer Ranch) around 4km upstream from Telkwa, northern BC. The goal of the Bulkley River Bank Stabilization and Riparian... -
Spring Creek Habitat Restoration Project
The Spring Creek Habitat Restoration Project was initiated under the Habitat Restoration Salmonid Enhancement Program to develop or improve coho salmon habitat in the Spring... -
Kitwanga River Side Channel Habitat Improvement Project
The Kitwanga River drainage is a tributary to the Skeena River located 90 kilometres northwest of Terrace, B.C. The Kitwanga River side channel habitat improvement project... -
Milgeelde and Kis daaw - An Aquatic Restoration Plan for the Clear Creek...
The Clear Creek Planning Unit (PU) restoration plan is prepared in a fashion that will provide useful background information for a wide variety of people interested in resource... -
Kalum South Literature Compilation and Database
In order to identify the existing Watershed Restoration program (WRP) grey literature in the Kalum forest district, The Terrace/Kitimat Partners for Salmonid (TKPS) contracted... -
Ecosystem Restoration and Compliance Monitoring Program 2002-2003
The report presents the result from routine effectiveness evaluations conducted before 2003. -
Ecosystem Restoration Opportunities in the Skeena Region
"This plan was developed as part of one aspect of the Ministry’s operations which is their Ecosystem Restoration (ER)1 program which is responsible for developing regional... -
Copper River Watershed Restoration Program: Copper River 3Km Off-channel Site
One project aim was the improvement of fish habitat. The site is located adjacent to the Copper River forest services road, between km 2 and 3, approximately 10 km east of... -
Fish Use Monitoring and Evaluation of Three Constructed Ponds within the...
This dataset contains a report evaluation the status of three constructed ponds in the Kalum Forest District. The ponds were constructed at Copper River 3 Km Off-channel Site,... -
Spawning Channel / Improved Spawning Habitat Project
This reports outlines the progress on four proposed projects in the Lakelse watershed in 2008/09 intended to improve spawning and incubation habitat for declining sockeye... -
Restoration Center of Expertise - SEHAB March 2023 Meeting
Presentation and slides for the Restoration Center of Expertise - SEHAB March 2023 Meeting, connected to the Pacific Salmon Strategy Initiative. -
Deep Creek Side Channel and Bank Stabilization
The Deep Creek side channel and bank stabilization project is intended as a demonstration project to create off-channel rearing and overwintering habitats for salmonids... -
McDowell Creek Culvert Replacement
This project focused on the replacement of a defunct culvert, that blocked fish access to 450 metres of important off-channel rearing habitat, approximately 130 metres upstream... -
Robert Hatch Creek Bridge Removal
This project focused on the removal of an old, collapsed wooden bridge where the creek passed through the Hatch Creek Ranch. Removal of this barrier and the restoration of... -
Cross Creek Culvert Replacement
This project focused on the replacement of two culverts close to Babine Lake, which became impassable to fish due to debris and low flow, especially at the time of year that... -
CN Trestle Bridge Channel Diversion and Revegetation
A failing slope was discovered below CN's Trestle Bridge at 8.8 mile on the CN Kitimat Subdivision, located approx. 10 km south of Terrace, BC. The unnamed creek (referred to as... -
Richfield Creek Riparian Exclusion Fencing and Restoration
Richfield Creek was included in a larger riparian restoration initiative in 2021 through the Morice Water Monitoring Trust (see dataset: Upper Bulkley Riparian Restoration). The... -
Spring Creek Project Dairy Street Landslide Rehabilitation
Spring Creek is a tributary to the Kalum River, close to Terrace. After a small landslide at the west end of Dairy Street in Terrace was discovered, which posed a potential...