Technical Data Reports for Enbridge Northern Gateway Project
Northern Gateway Pipelines Limited Partnership proposed to design, construct, and operate two pipelines extending from Bruderheim, Alberta, to Kitimat, British Columbia. Field surveys completed included sampling of fish species assemblages and habitat... -
Telkwa Coal Project: Application for a Project Approval Certificate
The Application should be read in the context that it is the basis for the first major stage of the Environmental Assessment Process as it applies to new mine developments proposed for British Columbia. The purpose of the Application is to provide an... -
Technical Data Report: Conceptual Freshwater Fish Habitat Compensation Plan E...
The objectives of this plan are three-fold. First, the plan describes the methods that will be used to quantify the amount of compensatory fish habitat needed to offset the harmful alteration, disruption, or destruction (HADD) resulting from the Project.... -
Pacific Trail Pipelines Project: Volume 1 Report - Application for Environmen...
This Application for an Environmental Assessment Certificate for the KSL Project has been prepared pursuant to Section 16(1) of the B.C. Environmental Assessment Act. The Application includes a description of the project, an outline of the Public and First... -
Pacific Trail Pipelines Application Volume II: Baseline Studies
These baseline studies cover the following topics with regards to the impacts of the Pacific Trail Pipeline: acid rock drainage and metal leaching, acoustic environment, air quality, archaeology, contaminated sites, fish and fish habitats, forestry,... -
Nisga'a Lands Freshwater Fish and Fish Habitat Technical Data Report for the ...
This report summarizes field data collected in 2014 for fish and fish habitat along the proposed application corridors within Nisga’a Lands. Fish and fish habitat information and field results for the remainder of the proposed project were collected in 2012... -
Kitimat - Summit Lake Pipeline Looping Project: Assessment Report
The purpose of this Assessment Report is to: describe the Project; summarize the process for the review of the Application; report on the adequacy of the Proponent’s distribution of information during the Application Review; report on whether the... -
Kitimat - Summit Lake (KSL) Pipeline Looping Project: Project Description
This project description has been prepared for submission to the B.C. Environmental Assessment Office (EAO) in accordance with the requirements of the B.C. Environmental Assessment Act. This environmental assessment will consider the potential effects of...