Environmental Assessment Office inspection records for the Northwest Transmission Line project. The Environmental Assessment Office (Chris PARKS, Compliance Officer) completed an inspection of portions of the Northwest Transmission Line Project against Conditions of EAC # E11-01, issued for the NTL Project. PARKS inspected construction works between New Aiyansh and the Bob Quinn Substation by truck and foot between November 26 and 29, 2013, and between May 13 and 15, 2014.