Wet'suwet'en Rights and Title and Enbridge's Northern Gateway Pipelines Project
The Office of the Wet'suwet'en (OW) presents this submission to the Northern Gateway Joint Review Panel. This submission is a component of the Wet'suwet'en response in respect of the proposed Northern Gateway project within Wet'suwet'en territory. The... -
Trout Creek/Kitseguecla Landscape Unit Plan
The Trout Creek Landscape Unit Plan (LUP) outlines the objectives and the strategies for the resource management of the Trout Creek and Toboggan watershed within the Bulkley portion of the Bulkley/Cassiar Forest District. The objectives address core... -
Telkwa Coal Project: Application for a Project Approval Certificate
The Application should be read in the context that it is the basis for the first major stage of the Environmental Assessment Process as it applies to new mine developments proposed for British Columbia. The purpose of the Application is to provide an... -
Reconnaissance Inventory of Damsumlo Lake
The Damsumlo Lake fish community was sampled with two standard experimental multi-mesh gillnets (one floating and one sinking) and five Gee-type minnow traps baited with salmon roe. Inlets and the outlet stream were sampled for fish presence by... -
Reconnaissance (1:20,000) Fish and Fish Habitat Inventory in the Upper Buck C...
This inventory provides information regarding the characteristics, distributions, and relative abundance of fish species, as well as information on biophysical lake and stream data. This information can be used for the interpretation of habitat sensitivity... -
Northwest Transmission Line: Bell-Irving Route Study
Sheffield studies and office-based reviews for this Bell-Irving Route Study Report were completed in August 2010. This report presents the results of baseline information collected as well as an evaluation of potential project effects on VECs along the... -
Morrison Copper/Gold Project Fish Habitat Compensation Plan
Pacific Brooker Minerals is proposing to develop the Morrison Copper/Gold Project on the east side of Morrison Lake, north of Babine Lake. The project will require the construction of a Tailings Storage Facility, including tailings and seepage control dams,... -
Babine River Interim Local Resource Use Plan
This plan describes the management consensus option and resource management issues for the Babine River area. It includes the watershed management prescriptions developed to meet the objectives of the consensus option.