Telkwa Coal Project Appendix 6: Baseline Data, Surface Water, and Groundwater...
Samples were collected for the first time from a watercourse on the proposed project site on the north side of the Telkwa, and from sites on the Telkwa River and Goathorn Creek which were previously sampled in 1988. Samples were also collected from the... -
Skeena Environmental Effects Monitoring (EEM) Pre-Design Reference Document
This document provides a basis for the design phase of an environmental effects monitoring program (EEM) for Repap's pulp and paper mill, Skeena Cellulose Inc., located near Prince Rupert, British Columbia. The pre-design document is essentially a "State of... -
Northwest Transmission Line: Bell-Irving Route Study
Sheffield studies and office-based reviews for this Bell-Irving Route Study Report were completed in August 2010. This report presents the results of baseline information collected as well as an evaluation of potential project effects on VECs along the... -
Davidson Project: Application for Environmental Assessment Certificate
This underground mining project will be located in the Bulkley-Nechako Regional District and in the traditional territory of the Wet'suwet'en people. Included in this dataset are the executive summary and elements of chapter six which deal directly with the...