Technical Data Reports for Enbridge Northern Gateway Project
Northern Gateway Pipelines Limited Partnership proposed to design, construct, and operate two pipelines extending from Bruderheim, Alberta, to Kitimat, British Columbia. Field surveys completed included sampling of fish species assemblages and habitat... -
Upper Bulkley River Steelhead Population Monitoring
The upper Bulkley River system, near Houston, was first assessed by the Fish Habitat Improvement Section in 1981. The initial assessment identified probably areas of importance for steelhead recruitment and juvenile rearing. In 1982 an index sampling... -
Technical Data Report: Conceptual Freshwater Fish Habitat Compensation Plan E...
The objectives of this plan are three-fold. First, the plan describes the methods that will be used to quantify the amount of compensatory fish habitat needed to offset the harmful alteration, disruption, or destruction (HADD) resulting from the Project.... -
Reconnaissance Report: Upper Bulkley River Steelhead Population Monitoring
The purpose of this report is to outline results of the 1983 steelhead fry recruitment monitoring program in the upper Bulkley system. The conclusion is that a larger fry population existed in 1983 than in 1981 or 1982. This data will serve as valuable... -
Northwest Transmission Line: Bell-Irving Route Study
Sheffield studies and office-based reviews for this Bell-Irving Route Study Report were completed in August 2010. This report presents the results of baseline information collected as well as an evaluation of potential project effects on VECs along the... -
Natural Resource Stewardship Monitoring and Assessment Report for the Wet'suw...
Natural Resource Stewardship Monitoring and Assessment Reports are a summary of existing resource value monitoring and assessment information for a given geographic area. Data in this report has been arranged into the following categories: fish and water,... -
Morrison Copper/Gold Project Assessment Report
This Assessment Report considers the proposed Morrison Copper/Gold Mine Project’s potential to cause significant adverse environmental, economic, social, heritage, and health effects. It identifies measures to prevent or reduce adverse effects, and sets out... -
Morrison Copper/Gold Project 3rd Party Review Response Report
This report presents the response to the 3rd Party Review of the Environmental Assessment for the Morrison Copper/Gold Project. The 3rd Party Review was requested by the Environmental Assessment Office and was mainly directed towards the hydrogeology, water... -
Kathlyn, Seymour, Round, and Tyhee Lakes: Water Quality Assessment and Object...
This study quantifies the inputs of phosphorus from various sources and determines the extent to which additional phosphorus could be tolerated by each lake without a serious decrease in water quality. Based on this information, appropriate land uses and... -
Fish Passage Assessment of Highway 16 and CN Rail in the Bulkley Watershed
This Bulkley fish passage assessment is part of a larger regional effort to improve fish passage limited by highways and secondary roads throughout the Skeena Basin. The purpose of this report is to present background information and survey results for fish... -
Fish Monitoring Studies in Buck, Foxy and Crow Creeks and Goosly Lake
These reports present the results of the 2012 and 2017 fish monitoring programs conducted in the vicinity of Equity Mine near Houston BC. -
Buck Creek Juvenile Salmon Trapping Programs
Juvenile coho, chinook, and rainbow trout/steelhead were sampled for the second and third consecutive years in Buck Creek using a rotary screw trap RST. The RST was sampled nightly to collect data on discharge, water temperature, and trap performance were... -
Assessment of Steelhead Enhancement Opportunities in the Morice River System
Juvenile salmonid populations in two tributary streams to the Morice River system, Owen and Lamprey Creeks, were assessed by the Fish Habitat Improvement Section in the fall of 1980. Objectives were directed at steelhead enhancement opportunities in the two... -
Aquatic Stream Inventory: Operational Stream Inventory in the Morrison IRM Un...
The overall purpose of this project was to conduct fisheries inventory in operational areas identified by Houston Forest Products in the Morrison Integrated Resource Management Unit (IRM). The objectives were to conduct a literature review of inventory... -
The Sockeye Salmon (Oncorhynchus nerka) of Morrison and Tahlo Lakes British C...
The purpose of this literature review is to provide a compilation of the published sockeye salmon fish literature on Morrison and Tahlo Lakes with references where appropriate to the much more extensive literature on Babine Lake. The focus of the report... -
The Potential Effects of Cadmium and Other Mixed Metal Mining Effluents on Fi...
This review is a qualitative assessment of existing data and a review of relevant primary literature. The objective of this review is to assess the potential effects of elements released from the Morrison Copper/Gold Project on fish assemblages in Morrison... -
Suskwa River Steelhead Trout: The 1977 Inventory, Creel Survey and Life Histo...
The 1977 aspect of the Suskwa River project began in July and continued until freeze-up in November. Fish were sampled either with "Gees" traps or by angling. The inventory crew switched to a casual creel survey and an adult steelhead tagging program during...